Spar Roundswell Service Station
Recent redevelopment of Spar Roundswell Service Station in Barnstaple. The development included the following works;
1. Liaising with Clients on design and layout of store
2. Strip back existing retail area to block walls
3. Uplift existing ceramic flooring
4. Installation of new ceramic floor 155sqm
5. Installation of Stud Walls
6. Installation of new joinery including Counter, perimeter boarding and end panels
7. Installation of new shelving
8. Installation of new FTG Prep Area
9. Installation of new suspended ceiling
10. Installation of new LED Lighting throughout
11. Full Electrical Works
Project duration: 7 Days (3 days closed)
Recent redevelopment of Spar Roundswell Service Station in Barnstaple. The development included the following works;
1. Liaising with Clients on design and layout of store
2. Strip back existing retail area to block walls
3. Uplift existing ceramic flooring
4. Installation of new ceramic floor 155sqm
5. Installation of Stud Walls
6. Installation of new joinery including Counter, perimeter boarding and end panels
7. Installation of new shelving
8. Installation of new FTG Prep Area
9. Installation of new suspended ceiling
10. Installation of new LED Lighting throughout
11. Full Electrical Works
Project duration: 7 Days (3 days closed)